Unique Top-selling OG0-092 Exams – New 2022 The Open Group Pratice Exam [Q16-Q39]

Rate this post

Unique Top-selling OG0-092 Exams – New 2022 The Open Group Pratice Exam

The Open Group Certification Dumps OG0-092 Exam for Full Questions – Exam Study Guide

Who Should Take Open Group OG0-092 Exam?

The Open Group Architecture Framework (TOGAF) is a method mostly used by firms in planning and designing their IT architecture. TOGAF specialists communicate with the heads of different departments, brainstorm, and work together to come up with an IT strategy that is both efficient and beneficial to the company. The audience for this exam is formed by individuals who want to know how to use the TOGAF 9 framework. Also, it is addressed to specialists who work in organizations that are already using TOGAF 9 features and want to learn how to participate in related initiatives and architectures. Besides, architects who want to take over responsibilities related to architecture artifacts are also welcome to take this exam. Another category is formed by architects who want to introduce TOGAF 9 architecture in the enterprise they are working for.

Certification Details

There are two pathways that lead to getting the TOGAF 9 Certified. One path includes completing two aforementioned exams separately while the second one offers to pass a single test that combines both of them in one sitting. To remind you, the required exams are Part 1 (OG0-091) and Part 2 (OG0-092). Part 1 will qualify you as a TOGAF 9 Foundation certified individual. It is recommended to finish the two parts in one day but you can choose to sit for the second part on the other day. Just make sure to bring a TOGAF 9 Foundation entry in the Directory of Certified People as proof that you’re eligible to take OG0-092 test.

 

QUESTION 16
Scenario: Vittronics Ltd.
Please read this scenario prior to answering the question
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity.
He has stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.
Refer to the Vittronics Ltd Scenario
You are serving as the Lead Architect for the SPICE project team.
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).
Based en TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 17
Scenario:
Please read this scenario prior to answering the question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario [Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]
One of the earliest initiatives in the Enterprise Architecture program was the definition of a set of architecture principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 18
Scenario: Armstrong Defense Industries
Please read this scenario prior to answering the question Armstrong Defense Industries is the prime contractor for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Armstrong Defense is moving aggressively to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
To achieve this goal, Armstrong Defense needs to define Baseline and Target Architectures. These architectures must address key stakeholders concerns such as:
1.What groups of people should be involved in procurement-related business processes?
2.What current applications do those groups use?
3.Which procurement-related business processes are supported by zero, one, or many existing applications?
4.What are the overall lifetimes of the Request for Proposal and Purchase Order business objects?
5.What non-procurement applications will need to be integrated with any new procurement applications?
6.What data will need to be shared?
At present, there are no particularly useful architectural assets related to this initiative. All assets need to be acquired and customized or created from scratch. The company prefers to implement existing package applications from systems vendors with little customization.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle.
Armstrong Defense is using TOGAF for its internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture Development Method (ADM) projects.
Refer to the Armstrong Defense Industries Scenario
You are serving as the Lead Architect.
You have been asked to identify the most appropriate architecture viewpoints for this situation.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 19
Carter Woods, a global furniture firm, wants to improve the efficiency of its sales force by replacing their legacy configuration and ordering systems based on manual and paper based processes with an online ordering platform.
Carter Woods uses the Architecture Delivery Method from TOGAF 9. The CIO sponsored this activity and the Baseline Architecture was defined on the initial iteration defining: approach, scope and architectural vision including a set of architecture principles related to the Data domain:
Data is an asset.

Data is shared.

Data is accessible.

A set of aspects to clarify arose from the business analysis from the assumption to replace the legacy systems with an online centralized one. These main concerns are:
To identify the changes to existing business processes.
To identify the data entities that can be shared among the sales agents.
To clarify how to keep the data secured.
To identify the list of non-sales application to be integrated with the sales applications Refer to the scenario above You, as Lead Enterprise Architect, need to identify the most appropriate architecture viewpoints to address the concerns above mentioned.
Choose one of the following answers

 
 
 
 

QUESTION 20
Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
During the initial meeting of the Common ERP Deployment architecture project team, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 21
Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to “leverage the synergies” that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 22
Scenario: Marona Inc.
Marona Inc is a Fortune 500 Enterprise in the retail industry with retail store components manufacturing units and marketing outlets spanning the globe and having an annual turnover of 20 billion$ with more than 100,
000 employees world wide.
The CEO, CIO and the stakeholders of the ongoing EA projects are concerned about rising costs and as one measure want to do an investigation into the operational aspects of the realized Enterprise Architecture using TOGAF9.
The CIO approaches you as the Lead Enterprise Architect to carry out this exercise the stakeholder had voiced to him the following concerns:
They want to analyze the roles of the top management for each revenue earning service. Moreover, many of the HR related critical Search application component have become extremely slow. This needs to be diagnosed and rectified. Moreover there is no proper tracking of revenue from retail store component products over time.
There has also been a lot of unauthorized or unwanted access to many of the critical information.
Hence the mode of access needs to be strengthened and made much more secure. Another additional concern is the new launches and the progress of each of the launches over time.
Determine which of the following set of viewpoints are most appropriate to analyze and view in order to address this concern of the stakeholders.

 
 
 
 

QUESTION 23
Scenario
Please read this scenario prior to answering the question
You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.
The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to
“leverage the synergies” that had been intended when the company was formed. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF, which of the following is the best answer?

 
 
 
 

QUESTION 24
Scenario: Florian Flowers BV
Please read this scenario prior to answering the question
Florian Flowers BV is an international agricultural company exporting flowers and seeds worldwide. Florian is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, Florian wants to develop strong self-directed teams in each location. Florian also wants to define new business models that are profitable while reducing their impact on the environment. Florian management is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
Florians international operations are subject to various legal and regulatory requirements. In areas such as genetically modified seeds, governmental controls are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested to be informed about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the guiding framework for the development and evolution of the Enterprise Architecture practice.
Refer to the Florian Flowers BV Scenario
Florian management has engaged you as the Lead Consultant to assess the current situation.
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of all these parties.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 25
Scenario: Florian Flowers BV
Please read this scenario prior to answering the question
Florian Flowers BV is an international agricultural company exporting flowers and seeds worldwide. Florian is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, Florian wants to develop strong self-directed teams in each location. Florian also wants to define new business models that are profitable while reducing their impact on the environment. Florian management is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
Florians international operations are subject to various legal and regulatory requirements. In areas such as genetically modified seeds, governmental controls are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest- resistant seeds.
The Governing Board is concerned, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested to be informed about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the guiding framework for the development and evolution of the Enterprise Architecture practice.
Refer to the Florian Flowers BV Scenario
Florian management has engaged you as the Lead Consultant to assess the current situation.
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of all these parties.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 26
Scenario
Please read this scenario prior to answering the question
You have been appointed as a consultant to the Chief Enterprise Architect of a multinational pharmaceutical corporation. The corporation includes 30 subsidiary companies with operations in over 60 countries and products sold in over 125 countries. It has major research and development sites in over 45 locations worldwide.
The management team is deeply committed to ensuring that the corporation is a world leader in socially responsible pharmaceutical development with a business strategy that focuses on profitability through environmentally friendly operating processes as well as a commitment to disease eradication.
The operations of the corporation are subject to legal and regulatory requirements for each country where they operate. The production of prescription pharmaceutical products has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was conducting a clinical trial for a new regulated drug.
The Governing Board is concerned about the risks posed in this complex global environment. As a result the Chief Executive Officer (CEO) has appointed a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues for the corporation. The CCO reports directly to the CEO.
The CCO has approved the expenditure of resources to establish an Enterprise Architecture program. He has requested to be informed about the status of projects that could impact regulatory compliance. He also wants the corporate legal staff and auditors to analyze all proposed architectures to ensure that they are within the legal guidelines for each country. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance Officer, legal staff, auditors and the research organization.
Based on TOGAF, which of the following is the best answer?

 
 
 
 

QUESTION 27
Carter Woods, a global furniture firm, wants to improve the efficiency of its sales force by replacing their legacy configuration and ordering systems based on manual and paper based processes with an online ordering platform.
Carter Woods uses the Architecture Delivery Method from TOGAF 9. The CIO sponsored this activity and the Baseline Architecture was defined on the initial iteration defining: approach, scope and architectural vision including a set of architecture principles related to the Data domain:
* Data is an asset.
* Data is shared.
* Data is accessible.
A set of aspects to clarify arose from the business analysis from the assumption to replace the legacy systems with an online centralized one. These main concerns are:
To identify the changes to existing business processes.
To identify the data entities that can be shared among the sales agents.
To clarify how to keep the data secured.
To identify the list of non-sales application to be integrated with the sales applications Refer to the scenario above You, as Lead Enterprise Architect, need to identify the most appropriate architecture viewpoints to address the concerns above mentioned.
Choose one of the following answers

 
 
 
 

QUESTION 28
Scenario: AGEX Inc.
Please read this scenario prior to answering the question
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to “leverage the synergies” that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise Architecture program.
The CIO has endorsed this choice with the full support of top management.
Refer to the AGEX Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 29
Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems.
It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 30
Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 31
Scenario: MegaMart
Case Study Title (Case Study):
MegaMart is a Retail Chain which has expanded throughout India and the Far East.
The CEO and CIO decide that there is a crying need to put an Enterprise Architecture in place to realize MegaMart’s strategy to expand its revenue and diversify. The CIO has evaluated and decided to go in for TOGAF9 and adapt it to his enterprise requirements.
The Preliminary and Vision Phase have been completed.
As such very few architectural artifacts exist and the target architecture as of now is not very clear. As the Lead Architect how would you guide your team of architects for the Business Architecture definition?

 
 
 
 
 
 
 
 

QUESTION 32
ARTI Dimensioning is a multinational that operates production facilities in 29 countries and sells its products in
over 120 countries.
A consultancy firm has recommended a realignment that will enhance sharing of product information across
business units. The implementation of this strategic realignment will require the development of integrated
customer information systems and product information systems.
ARTI has a mature enterprise architecture practice and uses TOGAF 9 for the basis of the ARTI Architecture
Framework (method and deliverables). The CIO is sponsoring an architecture development program that is
going to start. The CIO is concerned about a potential disruptive result to the business of this activity and
before proceeding with the architecture development he asked to evaluate the impacts on the company
business.
Refer to the scenario above
You are the Lead Architect and you have been asked to recommend an approach to address the concerns
raised. Based on TOGAF 9 recommend which of the following is the best answer.
Choose one of the following answers.

 
 
 
 

QUESTION 33
Scenario
Please read this scenario prior to answering the question
You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company.
The company has over 20,000 outsourcing professionals and works on some of the world’s largest outsourcing projects. Outsourcing services include business processes, infrastructure, and service management. The company also provides business consulting services.
With numerous service areas and a large number of diverse engagements in progress at any given time, overall engagement management within the company has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings.
The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised of IT staff executives and executives from the major service areas and consulting practice.
The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The EA team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains.
They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the vice presidents across the company that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF, which of the following is the best answer?

 
 
 
 

QUESTION 34
Scenario
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a multinational semiconductor and software design company. Its largest business is in processors, although it also designs system-on-a-chip infrastructure and manufactures memory chips. A characteristic feature of its processors is their low electric power consumption, which makes them particularly suitable for use in portable devices. As well as licensing its technology, the company has several manufacturing divisions.
The company has a mature enterprise architecture practice and uses TOGAF Standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management.
The EA program is sponsored by the CIO.
The company has defined a strategic architecture to improve its ability to meet customer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in the divisions’ production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company’s primary data center.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.
They have also completed the Implementation and Migration Plan v0.1, the draft Architecture Roadmap, and the Capability Assessment deliverables.
Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.
Refer to the Scenario
You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF Standard Version 9.2, which of the following is the best answer?

 
 
 
 

QUESTION 35
Scenario:
Please read this scenario prior to answering the Question
Your role is that of Lead Enterprise Architect within a vacation property management firm that has been growing through acquisition. The firm manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed on each property is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis.
The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year.
These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields.
The firm has a mature enterprise architecture practice and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO’s vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the firm has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
Refer to the scenario
You have been asked by the Chief Architect to justify the best approach for architecture development to realize the CEO’s vision.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 36
Scenario: Glacier Ridge LLC
Please read this scenario prior to answering the question
Glacier Ridge LLC is a vacation property management firm that is growing through acquisition. It manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed en each property is that they use a standard financial reporting system to report their financials ID the headquarters on a weekly basis. The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the Glacier Ridge property business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year. These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields. Glacier Ridge has mature enterprise architecture (EA) practice and uses TOGAF 9 as the method and guiding framework.
The CIO is the sponsor of the activity. In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO’s vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial engagement, Glacier Ridge has embraced an Architecture Vision to adopt an enterprise application that is tailored to the needs of the hospitality industry.
Refer to the Glacier Ridge scenario
Your role is that of Chief Architect. You have been asked to recommend the best approach to take in this architecture engagement to realize the CEO’s vision. Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 37
Scenario: AGEX Inc.
Please read this scenario prior to answering the question
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information.
The inability to share information across businesses has resulted in lost opportunities to “leverage the synergies” that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise Architecture program.
The CIO has endorsed this choice with the full support of top management.
Refer to the AGEX Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 38
Scenario: Summer Seeds BV
Please read this scenario prior to answering the question Summer Seeds BV is an international agricultural company exporting bulbs, flowers and seeds worldwide. It is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities. To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes. Summer Seed’s international operations are subject to various legal and regulatory requirements. In areas such as genetically modified seeds, governmental controls are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest- resistant seeds. The Governing Board is concerned, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested information about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs. TOGAF 9 has been mandated as the guiding framework for the development and evolution of the Enterprise Architecture practice.
Refer to the Summer Seeds BV Scenario You have been appointed as the Lead Consultant. You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of all these parties. Based on TOGAF 9, which of the following is the best answer?

 
 
 
 

QUESTION 39
Dante Manufacturing is a big supplier in the automotive industry, head quarter in London with main plants in New York, Milan, Toronto and Tokio. Each one of these plants has been operating its own Manufacturing Requirements Planning (MRP II) system, production scheduling and custom applications for production automation. Dante’s objective is to minimize waste production improving production operations. During an analysis of the process improvements was determined that a significant improvement on waste production could be achieved replacing the outdated MRPII system with a common Enterprise Resource Planning (ERP) located in London. Dante has well-developed governance and processes based on TOGAF 9. The Chief Engineer of Global Manufacturing operations is the business sponsor and issued a Request for Architectural Work. The architectural activity for the implementation of the new ERP platform is kicked off and the architectural vision is produced. Some concerns on the security, reliability, responsibility and time to manage change of driving the MRP II and production scheduling by a central system located in London are raised by the team of architects working on the project and by senior management of the various organizations. These last in particular, stressed the need to align the information management with the business.
Refer to the scenario above As Lead Architect you have been asked to update the IT architectural principles to address the concerns raised by the project stakeholders and the senior management. According to TOGAF 9 (assuming the enterprise is using the example set of principles in TOGAF 9 Section 23.6), which of the following is the best answer?
Choose one of the following answers

 
 
 
 

Best way to practice test for The Open Group OG0-092: https://www.it-tests.com/OG0-092.html

         

Related Links: www.stes.tyc.edu.tw www.stes.tyc.edu.tw www.stes.tyc.edu.tw myportal.utt.edu.tt www.stes.tyc.edu.tw myportal.utt.edu.tt